Most of the Master Cabin cabinetry has been installed, along with 30% of the day room. This process is moving along well and varnishing should begin in 6 weeks time. We are awaiting the foam padding element for the floating floor noise reduction system to come out of customs, after which the carpentry installation can begin in the rest of the vessel. Construction has begun on the final carpentry areas, the Captain’s cabin, the upper pantry, the upper day head, leaving only the bridge to get underway. The pre-manufacture of all of these areas in a warehouse speeds this process up considerably.